"This will be the first time the Oyster River has run free since the colonial settlers first began to dam the river there," Town Administrator Todd Selig told NHPR in July, adding that "the ecosystem will transition to its natural state." That was the summer view, with the pond drained and construction equipment parked in the middle of the old pond bed.
Four months later, the heavy work is done. According to the Town's October 30 Friday Update, the river channel restoration, the Mill Pond Road and Park restoration, and most other project tasks are finished. The project team made its last regular site visit of the construction season that week. The detour signs are about to come down. The site is still changing, though, because several parts of the project were scheduled to finish later than the excavators. The tide, the plantings, the fish run and the town's record of the old dam all run on separate schedules, and most of them reach into 2027.
The tide now reaches the old pond
Durham's 1913 dam was about 140 feet across and stood 13 feet high in structural height. It was the earliest known Ambursen-style dam in New Hampshire, built from evenly spaced concrete buttresses holding up a slanted upstream apron. For more than a century it split the Oyster River into a freshwater side and a saltwater side, as The New Hampshire described it in October.
That line has now moved. A photo in the Town's October 9 update shows high tide flowing up into the former Mill Pond area through the newly built river channel. The channel was shaped this summer and fall. Crews excavated sediment, graded and filled, placed boulders, stones, logs and root wads, and planted a riparian buffer along the banks. NHPR reported that engineers first located the river's natural channel and then rebuilt it, rather than designing a new one.
The water beside the Town Hall neighborhood used to sit at a flat pond level. Now it rises and falls with the tide coming up from Great Bay, so the river looks different from one hour to the next.
The Town has been direct about where not to stand to look. Its August update said the Route 108 bridge over the Oyster River has no sidewalk and is a high-traffic stretch where drivers don't expect people in the road. It also asked people not to cross private property for a view of the riverbed. That guidance still applies now that the water is moving again.
This week on Mill Pond Road
Mill Pond Road milling and paving are scheduled for the week of November 9, so the work falls in the days this post goes live. The road is closed during milling, paving and line painting, then fully reopens, and the detour signs come down. Mill Pond Road has had closures and a detour since construction began in the summer.
Paving is the most visible item on the punch list SumCo Eco-Contracting and VHB are finishing, but it isn't the only one. The October 30 update lists:
- Final plantings in the former impoundment along the Oyster River
- Mechanical removal of invasive buckthorn in several stands inside the former impoundment area
- Other miscellaneous cleanup
The two contracts behind this work were sized very differently. SumCo was awarded the $3,142,193 construction contract, and VHB the $394,950 contract for construction-phase engineering. NOAA and New Hampshire Department of Environmental Services grants were among the funding sources. NHPR described the whole effort as a $3.1 million project with about 60% covered by grants. The New Hampshire put that figure beside two others from the 2022 debate. Removal was originally estimated at $1.4 million, and repairing and maintaining the dam was estimated at $4.2 million.
The schedule after the crews leave
Here is how the rest of the project lines up, based on the Town's October 30 update and NHPR's July reporting:
| When | What happens at the site | Source |
|---|---|---|
| Week of Nov. 9, 2026 | Mill Pond Road milled, paved, striped and reopened | Town of Durham, Oct. 30 |
| Late fall 2026 | Final plantings and buckthorn removal in the former impoundment | Town of Durham, Oct. 30 |
| Winter 2026–27 | Durham Public Works and VHB inspect and assess the restoration | Town of Durham, Oct. 30 |
| Ongoing | Monitoring of the downstream fish migration and invasive plants | Town of Durham, Oct. 30 |
| Spring 2027 | SumCo and VHB return for minor replanting, repairs or adjustments | Town of Durham, Oct. 30 |
| Spring 2027 | Some native planting | NHPR, July 8 |
The Town says the spring return, which it calls adaptive management, is already in the project budget and is expected to be minimal. The banks of the old pond will look one way this winter and another once the spring planting fills in.
The fish the new river favors
The fish are the reason the schedule bent around the seasons. Contractors lowered the pond about 6 inches a day in June and waited until the seasonal fish run was over before starting. They coordinated with New Hampshire Fish and Game, which was watching for effects on birds and mammals along what Selig called a "wildlife highway."
Without the dam, migrating fish no longer need the old fish ladder and can move up the river on their own. According to NHPR's reporting on Fish and Game's assessment, removal opens about two miles of habitat in the lower river. Fish and Game also expects the faster current to favor blueback herring over alewives. The Oyster River is mainly considered a blueback herring run, although alewives have been seen in the Mill Pond fish ladder. In the October 30 update, the Town listed monitoring of the upcoming downstream fish migration among the parts of the project still underway.
Durham is the latest Great Bay tributary to go through this. The Winnicut River Dam in Greenland came out in 2009, and the Great Works Dam on the Exeter River came out in 2016. The Durham Conservation Commission, in its 2021 recommendation to the Town Council, said the removal "should serve as a springboard for expanded watershed-wide environmental stewardship activities" in the Great Bay.
A piece of the dam stays
The dam's history is also on a later schedule. Because the structure was historic, the project carries Section 106 mitigation requirements, and the Town lists coordination of a Historic Interpretation Program as unfinished work. Selig told NHPR the program would cover the dam's history and include a recording of the sound of the dam. He also said part of the dam would be preserved so visitors can understand what it did.
The minutes of the Town Council's May 18 meeting add another piece. The Heritage Commission had signed a memorandum of understanding for the Section 106 mitigation, and filmmaker Jerry Monkman would make the required documentary. The Town already has a written history of the dam online. NHPR cited it as the source for the dam's place in New Hampshire's engineering history.
The interpretation is part of how the decision was settled. The Department of Environmental Services flagged deteriorating concrete and exposed rebar in February 2018. The Town Council voted 7 to 2 for removal in 2021. In March 2022, 74% of town voters backed that decision. NHPR reported that some residents had wanted to keep the dam and the pond for their beauty and for recreation. The preserved section of dam and the documentary are how that version of the river stays on the record.
The pond, at the library through November
For now, the easiest place to see the old Mill Pond is indoors. The Durham Historic Association's exhibit "The Mill Pond Dam: A Retrospective" is at the Durham Public Library through the end of November, with paintings, photographs and historical information about the dam over the years. The association scheduled a November 10 reception upstairs at the library and invited people to bring a favorite photo, poem, memory or story about the pond or the dam. The exhibit continues after it, so the pond's long history is on the library walls in the same weeks the paving crews finish outside.
Another Durham institution is also marking a long run this month. Durham House of Pizza, known to generations of residents and UNH students as DHOP, celebrates 50 years in November. Stephen Petrovitsis and his father, James, opened it in 1976, and brothers Justin, Jordan and John run it today. Foster's Daily Democrat covered the family's history in an October 26 feature.
Questions about the river work can go to Town Engineer April Talon at 603-868-5578.